Scheduling built around operating-facility constraints.

Discuss Your Project →
Planning · Execution · Accountability · Results

Brownfield Construction Planning

Operating facilities introduce execution constraints that greenfield schedules may not encounter.

  • SIMOPS
  • Permit requirements
  • Restricted areas
  • Existing utilities
  • Isolation requirements
  • Tie-ins
  • Shutdown windows
  • Limited laydown
  • Congested work areas

Tie-In Planning

Tie-ins can become critical milestones requiring engineering, material, prefabrication, access, isolation, NDE, testing, reinstatement and startup to be coordinated before the window arrives.

Mechanical Completion & Commissioning

Construction can be connected to pressure testing, flushing, cleaning, electrical testing, loop checks, mechanical completion, pre-commissioning, commissioning and startup.